25th Avenue Project

                The completion of 25th Avenue from 6th Street to 13th Street will see final completion in the Spring of 2020.  The weather cooperated just enough, to give us an opportunity to pave the first layer of asphalt in November. The final lift of asphalt will be placed in Spring, when the weather is more conducive to paving.  The warmer temperatures will provide a better environment for the final layer of asphalt to bond with the binder course that was placed in November.  The final landscaping will also be completed in Spring, as soon as weather permits.  The City will continue to work on rough terrace restoration as weather permits during the month of December.