8th Street Construction Update

8th Street Construction Update for week ending 6/16/17

8th Street construction continued this week with very warm temperatures.  Crews completed Stage 1 concrete paving at the intersection of Highway 69 while also focusing on completing curb and gutter, sidewalks and driveways near the east end.  Storm sewer was installed from 4th Avenue to 5th Avenue and storm work was completed at 3rd Avenue.  While concrete and storm sewer crews worked on the east half of the project, a restoration crew began placing topsoil in the terrace on the west half.

Next week will be another busy week for the project.  Concrete crews will be working to complete all Stage 1 curb, sidewalk and driveway paving.  All the stage 1 storm sewer should be installed by the end of the week with electricians working on installing conduit for the traffic signals.  More curb and gutter and road base are planned from 3rd Avenue to 5th Avenue and crews should begin final grading operations in preparation for Stage 1 paving. 

Stage 1 work should be completed in the next 2 weeks, leading us into Stage 2 of the project.  You will begin to see new asphalt pavement, decorative stamped sidewalk, and changes to the traffic patterns.  We will give additional updates over these next couple of weeks but ask that you continue to keep an eye out for workers and other vehicles as you travel through the construction zone. 

Have a great week!     

JESSE DUFF, PE  I  Sr. Project Engineer

Fehr Graham – Engineering & Environmental

1107 16th Avenue

Monroe, Wisconsin 53566

P: 608.329.6400

C: 608.636.3833

F: 608.325.2797

www.fehr-graham.com

KEN PLOWMAN I  Senior Engineering Technician

Fehr Graham – Engineering & Environmental

 

1107 16th Avenue

Monroe, Wisconsin 53566

P: 608.329.6400

C: 815.238.0032

F: 608.325.2797

www.fehr-graham.com

Facebook Twitter Google Plus Email

Other News in Home